Lake County begins Workday test planning; targets Dec. 1 go-live with six-week hypercare
Summary
Project manager Patrice Evans told the Technology Committee May 1 that Workday testing will begin in June after mid-May scenario creation, testing should finish by August and the county is targeting a Dec. 1 go-live; Strata will provide six weeks of post-go-live hypercare.
Project manager Patrice Evans updated the committee May 1 on Lake County's Workday ERP implementation timeline and risks, saying the program is moving from configuration into testing and that the county is preparing for an aggressive test schedule.
Evans said the transformation alignment and the governance charter are complete and that the team is currently finishing foundation data model…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat