Council approves $16.35 million guaranteed‑max price for Fire Station 6, a multiuse west‑side facility

Town Council of Flower Mound, Texas · May 4, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Town Council approved a construction agreement with a CMAR and a guaranteed‑max price (GMP) of $16,354,546 for Fire Station 6, a multiuse facility on the west side that will include apparatus bays, police office space, community classroom areas and a library pickup/reading pods.

The Town Council on May 4 approved a construction agreement and guaranteed‑max price (GMP) for Fire Station 6, a multiuse facility planned for the town’s west side.

Dean Larson reported that the design phase is complete and the town negotiated a GMP with Crossland Construction under a CMAR delivery model. The GMP presented to council was $16,354,546. Larson described the CMAR structure as a cost‑of‑work plus fee model with a guaranteed maximum that can be lower but not higher unless the town requests changes.

Justin (Martinez Architects) reviewed design features: four double‑stacked apparatus bays, separate personnel living/dorm areas with improved sleep and decontamination facilities aligned with NFPA guidance, a community training room divisible by curtain walls, library service pods and a public trailhead. The facility also includes space for police offices and a nonpublic storm shelter for building occupants as required by local code.

Council asked about schedule commitments and penalties; staff said the CMAR set a substantial‑completion date and liquidated damages provisions apply for missed dates (no milestone incentives were included). The team targeted a May groundbreaking, a June construction start and roughly 16 months to substantial completion.

A motion to approve item K3 (construction services / GMP) was moved, seconded and passed by unanimous roll call.

What’s next: staff anticipates coordinating a groundbreaking ceremony (tentative May date), starting construction in June and returning to council during construction as needed for updates or to address potential scope changes.