Utilities superintendent reports five sealed bids for Lawrence inflow-and-infiltration project; project updates given

Lawrence City Utility Service Board · March 25, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The utilities superintendent reported a March 13 public bid opening for the Lawrence 46 and Post Road I inflow and infiltration removal project at Community Park, saying the city received five sealed bids and that a consultant is reviewing packages before a recommendation to the board.

The utilities superintendent told the Lawrence City utility board that a public bid opening on March 13 produced five sealed bids for the Lawrence 46 and Post Road I inflow-and-infiltration removal project at Community Park.

He reported the bids as Performance Pipe Lining — $2,227,499.50; Inlander Solutions — $2,656,130; ELD Services — $1,894,725; CitroForm Technologies — $1,837,000 and SLB Pipe Solutions — $1,822,135. One bid amount in the transcript includes formatting that is unclear ('70 $762.76'); the superintendent acknowledged American Structure Point is still reviewing bid packages for completeness and accuracy.

The superintendent said, "Barring any unforeseen circumstances, we should have a noticeable word to present to you at the next meeting," indicating the city expects to return with a next-step recommendation after consultant review. He also updated the board on ongoing projects, saying the Fort Harrison capacity improvements project (phase 3) and the 71st Street Lift Station base inflow-and-infiltration removal project should be completed by April, with final restorations and street cuts to follow.

Why it matters: the board must review consultant findings before authorizing contract awards; the projects address sewer inflow and infiltration that can affect system capacity and street restorations.

The superintendent attributed the bid-review work to American Structure Point and did not give a firm award date beyond the expectation of presenting an update at the next meeting.