Scranton SD awards Monticello East contracts after bids exceed estimates; district faces near-10% construction overrun

Scranton School District Board of Education · May 5, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Scranton School District approved general-contractor and trade contracts for the Monticello East project after bids exceeded the district's 50% design estimates; staff cited an accelerated schedule, added scope and contingency buys that pushed the project about 9.9% over budget.

The Scranton School District on May 4 awarded the principal construction contracts for the Monticello East project but acknowledged the work came in notably above earlier budget estimates.

District staff recommended awarding the general-contractor contract to Panzida Enterprises at $3,590,500 and separate mechanical, electrical and plumbing contracts to Scranton Electric Heating & Cooling Services ($1,094,264 recommended), Urban Electrical Contractors ($1,467,500 recommended) and G. Ritzick & Sons ($449,650 recommended), for a combined contracting total of $6,649,842. The board approved those contract awards by roll call vote.

In presenting the bids, the district's construction manager told the board the 50% design-phase…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered summaries by topic, speaker, decisions & budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans