Summary

Committee members supported Phase 1 of the city's mobility plan, recommended moving Phase 2 forward with roughly $45,000 to support design and grant readiness, discussed a roadway-characterization plan to send to council and continued negotiations with property owners over easements and offers up to $20,000.

Pataskala City officials advanced several transportation items at a committee meeting, voting to support Phase 1 of the mobility plan and recommending Phase 2 be authorized for more detailed planning. Presenter (S2) told the group Phase 2 would add refined cost estimates, stakeholder meetings and a clearer strategy for pursuing grants and other funding.

The committee also heard results from community engagement. Presenter (S3) said residents ranked proximity to hiking, biking and walking highly—"3.9 out of a 5 total"—and that the input shaped the plan's priorities for pedestrian and bicycle infrastructure. Presenter (S2) said Phase 1 produced a prioritized list of 10 projects and that Phase 2 will target specific gaps in the pedestrian mobility network and identify potential funding sources.

On the motion to support Phase 1 and move Phase 2 forward, members indicated support and staff noted an expected authorization of roughly $45,000 to complete the next scope of work needed for grant applications and detailed design. Committee discussion made clear the primary purpose of the funding is to produce the documentation and cost estimates grantors typically require rather than to build improvements immediately.

Separately, the committee reviewed a roadway-characterization plan (referred to in the discussion as the "third" plan) that recommends cross-section widths, materials and character types to guide right-of-way acquisition and developer-required improvements. Presenter (S2) framed the characterization as complementary to the comprehensive plan; Committee member (S5) moved to recommend the characterization plan to the city council for further consideration, and members registered support during roll call. A potential council consideration date of April 6 was mentioned during the discussion.

Committee members also discussed the 2026 street program and related property transactions. Presenter (S2) described two negotiations to acquire or secure easements: one owner negotiated to a figure around $15,000, while another owner, identified in the discussion as Mr. McCord, has proved more difficult. Staff said offers had ranged between $10,000 and $15,000 in cash or equivalent work and that the city set a firm maximum offer of $20,000 (cash or goods/work) with a one-week response window. Presenter (S2) said the city authorized an initial $10,000 to cover legwork and preparation needed for the process if negotiations require it.

Participants flagged a water-line easement and a homeowner's geothermal heating lines that may lie within proposed right-of-way, prompting plans for further coordination with the affected property owner. The committee also reviewed an exhibit showing proposed roundabouts on Broadway and other local streets; Presenter (S2) said roundabouts could reduce cut-through and cross-access movements. Members noted there are limits on what the city can do on state routes and emphasized coordination with state agencies for truck restrictions.

The meeting closed with committee members indicating formal support to forward the transportation items and the roadway-characterization plan to the city council for action. Staff said the additional studies and negotiations are intended to both refine design options and strengthen the city's case when seeking outside grant funding.