Pitt County Schools OKs $541,580.52 data‑center replacement to avert outages
Summary
The school board approved a $541,580.52 replacement of district data‑center equipment, citing outages and loss of vendor support; the superintendent’s staff said the work will be completed over the summer to avoid instructional disruption.
Get email alerts on the Technology Infrastructure topic
No spam. Unsubscribe anytime.
Pitt County Schools’ board on May 6 approved a $541,580.52 complete replacement of the district data center, moving to update hardware officials said is more than a decade old and increasingly unsupported by vendors.
Julie Simpson, who presented the request, told the board the district’s data center “is the backbone of our district's technology system” and said equipment failures have caused outages during testing and day‑to‑day operations. She said the current system is no longer covered by vendor service and “our technicians have to figure it out, which takes us a significantly longer period of time to get it back up and working.”
Simpson gave a single cost estimate for the project and said the work would be completed over the summer so “it won't affect instruction in any kind of way.” Board members asked for additional detail before voting; a board member moved to approve, the motion was seconded and the board voted in favor.
The board did not attach a public line‑item budget breakdown during the meeting; Simpson said technology had been saving funds over several years to cover the upgrade. The board’s formal action approved the request to replace the district data‑center hardware and proceed with contracting for the work.
Next steps identified at the meeting include completing procurement and scheduling the work for summer months to avoid impacting classes and testing.