Tigard delays River Terrace 2 adoption, asks council to weigh policy trade-offs on street designs
Summary
City staff delayed the adoption timeline for River Terrace 2 by five months to April–May 2027 to allow more time for code amendments and finance strategy work, and told council it will ask for direction on two contested street designs on May 26; staff also plans a citywide study of tiered SDCs and opted not to create a supplemental maintenance fee for River Terrace 2 residents.
City staff told the council the River Terrace 2 community plan will move more slowly: adoption previously scheduled for late this year has been pushed back by five months to April–May 2027 to allow additional time for development-code amendments and a coordinated finance strategy.
At a study-session presentation the senior planner said city leadership will advance a study on tiered system development charges (SDCs) citywide and in River Terrace 2 to support housing production and…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat