Highway Department reports progress on bridges, ARPA stormwater projects and resurfacing plans
Summary
County highway staff told commissioners the Green Bridge project is closed out, several bridge and roadway projects are in design or right-of-way negotiation, and roughly $2.5 million in ARPA stormwater construction was completed last year; commissioners were briefed on upcoming resurfacing and equipment purchases.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
County Highway Department staff told the Christian County Commission on the first quarter's progress, saying the Green Bridge project is complete and that several bridge and roadway efforts are in active design or negotiation.
"The Green Bridge project is completely closed out. Invoices are final," said the agency official who presented the report. The presenter said the county completed the Green Bridge reassembly at the campus earlier than planned and installed a historic marker and a marker for Todd's Trail.
Staff said the Forest Service has advertised an older structure as part of the historic-preservation process and that at least one submittal for alternate use is under review; the county is designing replacement trusses so the older structure can be incorporated into the new bridge even if an outside party does not assume stewardship.
Multiple roadway projects were described as moving forward: the Chadwick Road over Cedar Creek design is ranked and under contract review for federal-lands access funding; Sanders Valley safety improvements are in right-of-way negotiations with temporary construction easements pending; and a Tracker and Nicholas Road improvement is being managed through a memorandum of agreement with the OTO regional body.
On stormwater, staff said the county completed about $2,500,000 worth of ARPA-funded stormwater construction last year and that five design projects remain to be finished this year. The presenter described ongoing work on Oldfield Road, Merritt and Carib stormwater designs, and the narrow, hilly Jonesville Road improvement that will require widening for safety.
The department also reported operational metrics: 72 service requests in the quarter with approximately 97% closed and an average open-request duration of three days; about $101,000 in asphalt work and $35,000 in culvert work completed in Q1 were cited as examples of maintenance activity.
Commissioners asked about timeline impacts and funding, and the presenter noted that work often depends on external approvals (for example, FEMA reviews on certain requests) and on seasonal factors such as asphalt-plant openings. The commission praised crews' storm-response work during a winter snow event.
The highway presentation concluded with updates on equipment purchases (new backhoe and mini excavator were highlighted), CDL training outcomes, ongoing sign-inventory work under a TEEP grant, and planned resurfacing and widening lists for the summer.
The commission did not take a formal vote on new policy but asked staff to return with specific proposals or contract documents when needed.