Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the School Facilities topic
No spam. Unsubscribe anytime.
School board approves field-house change order, ratifies multipurpose building bid and accepts South Fork Junior High as substantially complete
Summary
The board approved a $278,797 change order and 30‑day extension for the Denham Springs High School field house, ratified Macklin Construction as low bidder for a multipurpose building at $2,919,000, approved a credit change order for South Fork Junior High, and accepted South Fork as substantially complete.
Get email alerts on the School Facilities topic
No spam. Unsubscribe anytime.
The Livingston Parish School Board approved several construction and procurement actions covering Denham Springs High School and the new South Fork Junior High School.
Jeff LaRosa of Coleman Partners Architects presented Change Order No. 4 for the Denham Springs High School new field house and renovations, describing the change order as "in the amount of $278,797 in a 30 day extension to the contract for Blunt General Contractors LLC," and listing work that included added guardrails for a second‑floor patio, exterior canopies, an egress gate with panic hardware, finish upgrades to the existing field house, coach shower drain modifications and a concrete ramp and landing at an exit door. Consultants reviewed the submission and recommended approval; the board moved, seconded and approved the change order.
On a separate item, staff reported the apparent low bidder for the district multipurpose building was Macklin Construction at $2,919,000; staff said they had spoken with the bidder (McGlynn) and recommended entering into a contract. Doctor Ron McMorris moved to ratify the bids, Miss Cecil Harris seconded, and the board approved the ratification.
Jim Zilar of Zilar Architects asked the board to approve Change Order No. 4 for the South Fork Junior High School project; he described it as a credit of $15,990 that would reduce the original contract sum by $91,149.50 and produce a new contract price of $21,377,850. The board approved the credit by voice vote. Zilar then asked the board to accept South Fork Junior High School as substantially complete, noting remaining punch‑list items were chiefly cleaning and minor repairs and praising Weatherblunt Corporation's construction work; the board approved substantial completion.
Motions on the construction items were made, seconded and carried by the board. The meeting record does not specify contract execution dates or detailed schedules; staff and project consultants were listed as recommending approval for the presented items.

