Vienna council keeps $300,000 placeholder for annex development after packed public hearing on proposed aquatic center
Summary
After hours of public comment, council members voted to retain a $300,000 line in the FY27 draft budget — renamed “future development of the town‑owned property at 301 Center Street South” — rather than remove funding for the proposed annex aquatic and fitness center.
Get email alerts on the Budget Annex Pool topic
No spam. Unsubscribe anytime.
Dozens of Vienna residents packed the Town Hall on April 6 and urged the Town Council to remove the annex aquatic and fitness center from the proposed fiscal‑year 2027 budget, citing construction estimates of $28 million–$36 million and projected annual operating shortfalls. After nearly three hours of testimony and internal debate, the council voted to keep $300,000 in the draft budget as a placeholder and to rename the line "future development of the town‑owned property at 301 Center Street South."
The vote followed public testimony from residents who said the proposal would burden taxpayers and duplicate nearby private and county pools. "This is not a self‑sustaining investment," Mary Flynn told the council, citing a $500,000 pledge the town has received and urging a referendum so voters could decide. Bill Commerford warned councilors that similar facilities in other towns have required long‑term subsidies, saying town staff estimate a $1.6 million annual operating subsidy and $60 million in cumulative costs over 20 years.
Supporters characterized the project as a long‑term community amenity. "This is a long‑term improvement for Vienna," Aaron Georgalos said, adding that convenience and year‑round access matter for some residents. Council members said the council must balance those community benefits against fiscal risk and public sentiment. Council member Baldwin said design work and community fundraising remain possible but that the council should be transparent about the tradeoffs; he moved to rename the budget line to emphasize the property’s future development rather than lock in an aquatics project.
Council member Anderson said he opposed setting aside money now for anticipated operating losses. Council member Nash described the $300,000 as a prudent placeholder that allows staff to continue limited planning without obligating the town to finalize a large capital commitment. Council member Springsteen called the pool idea "aspirational" but said current numbers and resident sentiment counsel pausing further advancement. The motion to rename the line item and advertise the budget passed by recorded vote.
What happens next: the council directed the town clerk to advertise a notice of intent to adopt the FY27 budget for May 18, 2026, and left the written public‑comment period open for one week. The council also scheduled additional work sessions and an April 27 agenda item related to awarding a project manager for the annex site — a decision that councilors said would be separate from the budget adoption process.