Adams County cites delays on Cherry Fork sewer, submits Locust Grove LOI and wins $1.25M for Winchester wastewater upgrade
Summary
Economic Development reported weather-related delays on the Cherry Fork sewer project, submitted a Letter of Intent for Locust Grove sewer funding, and announced a $1.25 million Community Project Fund award for Winchester wastewater plus $4 million in principle forgiveness from the Ohio EPA.
Get email alerts on the Economic Development topic
No spam. Unsubscribe anytime.
Economic Development Director Paul Worley updated the commissioners on several water and wastewater projects in Adams County on Feb. 2.
Mr. Worley said weather events have delayed work on the Cherry Fork Sewer Project. He reported the county submitted a Letter of Intent for Locust Grove Sewer to the Ohio Valley Regional Development Commission for potential funding.
The board was told the Winchester Wastewater Treatment Project received a $1,250,000 Community Project Fund award and that the Ohio Environmental Protection Agency (Ohio EPA) approved $4,000,000 in principle forgiveness for the project. Water tower construction at the Winchester Industrial Park is scheduled to begin in May 2026. Worley also noted the Adams County Training Center has six students enrolled in the adult HVAC program.
The update covered project status, funding milestones and next steps; the minutes record these as informational updates rather than discrete board actions.