Three bids opened for Brush Creek Road bridge replacement; lowest bid at $1.87 million

Board of Adams County Commissioners · April 13, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

At a public bid opening April 13, Adams County read three proposals for the Brush Creek Road Design‑Build Bridge Replacement. Cooper’s Excavating submitted the lowest bid at $1,871,863; bids were turned over to county Engineer Lee Pertuset for review.

The Board of Adams County Commissioners opened bids at 9:15 a.m. on April 13 for the Brush Creek Road Design‑Build Bridge Replacement project.

The county read three bids: DGM at $2,100,000.00; Cooper’s Excavating at $1,871,863.00; and ORDERS Constructions at $4,742,000.00. Following the reading, the bid packages were turned over to Engineer Lee Pertuset for evaluation and recommendation to the board.

Those present at the opening included Engineer Lee Pertuset, Sam Cooper representing Cooper’s Excavating, and Eli Eaton, business manager for DGM, Inc. No award was made at the opening; the board will rely on the engineer’s review to determine responsiveness, responsible bidder status and any recommendation for contract award.

The bid opening is part of the county’s procurement process for infrastructure projects; commissioners did not take a final vote on award during the session.