Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Veregey Pump Stations topic

No spam. Unsubscribe anytime.

Commissioners approve $608,669.33 invoice for Veregy pump-station work

Washington County Commissioners · April 2, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Washington County approved Invoice #3 for the Veregy Pump Station Improvements Project — Phase 2, authorizing payment of $608,669.33; the minutes report progress of 95% completion on eight pump stations and 50% on nine others.

Washington County commissioners on April 2 approved Invoice #3 for the Veregy Pump Station Improvements Project — Phase 2, for $608,669.33.

The minutes state the invoice covers field-work installation and reports 95% completion of eight pump stations and 50% completion of nine pump stations. Veregy is identified in the minutes as the Construction Manager at Risk for the project. Eddie D. Place moved the invoice approval and Ronald G. Nohe seconded; the motion passed on recorded roll call (Schilling, Place, Nohe — all aye).

The approval authorizes county finance staff to process the payment in accordance with contract terms and project accounting. The County Engineer or project manager is responsible for ongoing project oversight and reporting to the board.

Why it matters: This is a sizable payment on a county infrastructure project; the minutes document both the dollar amount and the reported completion percentages for portions of the scope.