Tequesta council approves $3.5M Beach Road water‑main contract, plus multiple water-system projects and upgrades

Village Council of the Village of Tequesta · May 5, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved the SRF‑funded $3,540,449.60 contract for the Beach Road water‑main replacement and several related water-system contracts and work authorizations, including a $153,817.85 construction-administration authorization and access-control upgrades at the water plant.

The Village of Tequesta council on April 9 approved multiple contracts and authorizations to advance water-system work, including a SRF‑funded contract for the Watermain 2 Beach Road replacement and a package of related professional and construction work.

Key approvals: the council awarded the main construction contract for the Beach Road water‑main replacement to Amici for $3,540,449.60; the project is expected to be reimbursed through the State Revolving Fund (SRF) loan and staff estimated roughly 210 days to substantial completion. Council also approved a $153,817.85 work authorization with Kimley Horn for construction-administration services (inspection, permitting, shop-drawing reviews and pay-application oversight) for Watermain 2, and approved a piggyback agreement with Miller Electric to install access controls and a camera/intercom at the water treatment plant and to add badge access at the maintenance building.

Other water-related items: council approved Change Order No. 3 for filter‑vessel rehabilitation with Florida Design Contractors (to address exterior coating over weld burn-through marks), accepted final pay application processing for filter-media and membrane replacement projects nearing substantial completion, and approved a contract with Cone and Graham for Tequesta Drive bridge restoration ($985,282) that staff said addresses concrete and steel work affecting water/right-of-way access.

Funding and timing: staff said the Beach Road construction will be SRF-funded (construction funds are reimbursable under the SRF loan that the village earlier secured), and the SRF loan payment was included by finance staff in a concurrent budget amendment. Utilities Director Allison Berg also reviewed near-term milestones for Well 28 testing, SCADA conversion (target completion November), and water-treatment plant drawings (revised drawings due April 17 with a June bid timeline).

Why it matters: the water-main replacement and related upgrades are part of multi-year capital work intended to improve reliability and replace aging infrastructure; council emphasized coordination with SRF funding to reduce borrowing costs.

Next steps: procurement and construction milestones proceed according to contract schedules; public-notice and permit steps are ongoing for certain crossings and dredge/permit approvals referenced in the utilities report.

Sources: utilities standing report and the April 9 council agenda presentations and contract award motions.