Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Project Timing topic

No spam. Unsubscribe anytime.

Board sets Pleasant Hill Road completion date to June 30, 2026 after debate over contract wording

Board of Aldermen · May 6, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved a time-only change order (Change Order No. 2) for the Pleasant Hill Road widening project to revise the project completion date to June 30, 2026 after discussion about whether to phrase it as a total of 480 days or as a date-certain; the board accepted the city engineer's recommendation and approved the June 30 date.

The Olive Branch Board of Aldermen voted May 5 to approve Change Order No. 2 for Phillips Construction, revising the Pleasant Hill Road widening project completion date to June 30, 2026.

The discussion centered on whether the change order should be written as a total contract time (480 days) or as a date-certain completion. Multiple board members expressed concern about ambiguity in the wording. Legal counsel and staff advised that approving a date-certain completion (June 30, 2026) would allow the board to adopt a clear deadline and have staff calculate the precise number of contract days later.

"If June 30 date's accurate and then we've got a date certain that we're dealing with," legal counsel said, "we can provide the number of days later after Mister Swims has an opportunity to actually perform that calculation." Engineering staff and board members agreed; a motion to approve the city engineer's recommendation reflecting the June 30 date was seconded and passed.

The approved action revises the project's completion date to June 30, 2026; staff said they would provide the calculated total contract days in a follow-up calculation.