Supervisors rejected bids for the county courthouse expansion after hearing rebid electrical estimates and debating bonding, ARPA constraints and phased alternatives; board members directed staff to pursue a smaller redesign and clarify federal funding rules.

Bremer County supervisors voted to reject the construction bids for the county courthouse expansion after several supervisors raised concerns that the rebid total exceeded what the board is prepared to finance.

At an 11 a.m. construction update, county project staff reported the rebid produced a lower electrical low bid — "K and W Electric out of Waterloo" — at $639,936, with other electrical bids under $700,000. Staff said the new construction subtotal came in just under $9.985 million and the all-in owner total was about $11.106 million.

"We were pleased to see a lower electrical number come through," the project presenter said, but supervisors questioned whether the overall price remained too high. One supervisor summarized a financing model that used $6.3 million in bonding and fund-balance assumptions and said that approach would require roughly a $275,000 annual reduction in road spending to maintain solvency during the bond period.

"I can't support this," a supervisor said during debate, arguing the project had grown well beyond the initial entryway concept and that the county should pursue a more practical, smaller design. Another supervisor recommended redesigning the addition to preserve options for future expansion.

Board members discussed immediate alternatives — for example, completing essential items such as generator enclosure or air-handler work before a full rebuild — and raised questions about allowable uses of remaining ARPA funds for elements already purchased but not yet installed.

After discussion, a supervisor moved "to reject the bids as presented." The motion carried by voice vote; one supervisor opposed during the roll call. The board did not award a contract.

Supervisors instructed staff to reconvene next week with a redesign plan B, ask the construction manager to quantify redesign timelines, and have county staff (including Scott, Eric, Cassandra and the county attorney) review ARPA guidance and remaining obligations. The board also asked staff to explore whether portions of the project could be rephased or rebid more quickly.