Vienna moves forward on $2.8M smart-signal upgrade for Maple Avenue and Nutley Street; operation testing Aug'Nov 2025
Summary
Public works presented a VDOT SmartScale-funded signal upgrade to interconnect 14 intersections on Maple and Nutley, replace two intersections completely and add cameras and centralized traffic-management software; construction cost $2.8 million with substantial completion estimated August 2025 and operational testing through November 2025.
Brad Baer, director of public works, and the engineering team outlined the Maple Avenue and Nutley Street traffic-signal improvement project and answered detailed council questions about timing, features and operations.
Baer said design was completed in February 2023 (design cost $245,000) and construction was contracted in 2023 for $2,800,000 to Richardson Wayland Freer Electric Company. Construction began in 2024; staff said the contractor is about 75 percent complete with equipment in town and overnight work underway. Baer described an 18-month window of…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat