Planning Commission approves performance‑guarantee transitions and extensions for multiple Nolensville developments

Town of Nolensville Planning Commission · February 10, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The commission accepted completion updates and approved transitions to maintenance or time‑limited extensions for Annecy phases, Telluride, 7209 Nolensville Road (amended to six months), Village Green and a freestanding emergency room.

At its Feb. 10 meeting, the Nolensville Planning Commission approved a string of performance‑guarantee actions for local developments, accepting completion updates and moving several projects from performance sureties to maintenance periods.

Staff told the commission that Annecy Phase 3B and 3C landscaping work is complete; staff and the applicant’s representative, Jay Easter (S8), confirmed the plantings and agreed warranty periods should begin. The commission approved both the completion acceptance and the requested transitions to one‑year maintenance periods.

The commission also granted Telluride a nine‑month extension to its performance agreement after staff said the developer provided documentation and a surety in the amount of $705,247.50. Telluride’s representative said outstanding items included final topping and landscape buffering. The extension was approved unanimously.

For 7209 Nolensville Road, the applicant sought a 12‑month extension and posted additional surety to raise total surety to $83,992.50. Commissioners discussed outstanding sidewalk and detectable‑warning work and debated whether 12 months was necessary; a motion amended the extension to six months, and both the amendment and the amended motion passed unanimously. Staff will inform the applicant of the six‑month grant.

Village Green’s developer requested a one‑year maintenance transition and a reduction of surety contingent on that transition. Staff recommended approval; commissioners discussed storm damage to recently planted trees and warranty replacements. The commission approved the transition and reduction unanimously.

Finally, the commission approved transitioning landscaping surety for a proposed freestanding emergency room to a one‑year maintenance period. Staff confirmed that engineering and planning recommended the transitions in each case.

Commissioners framed these approvals as routine, but several asked staff to include attachments and detailed status information with the surety report in future agenda distributions so the public can review project statuses in advance.