Council approves $7M in bonds to repair high school and middle school roofs with MSBA reimbursement

Newburyport City Council · March 25, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Newburyport City Council approved two bond orders to fund roof replacements at the high school and Nock Middle School, leveraging an MSBA accelerated-repair program that reimburses about 43% of eligible costs; councilors pressed administration for fuller long-term debt and tax-impact analysis.

The Newburyport City Council on March 23 approved two bond orders to fund roof replacement projects at the high school and Nock Middle School, moving the projects into the Massachusetts School Building Authority (MSBA) accelerated-repair process.

Councilors were told the MSBA has accepted the city into the program and that the projects are eligible for roughly a 43% reimbursement. City staff and the project’s owner’s project manager described two separate roofing contracts — one for the high school (auditorium, library and older wings) and one for the middle school — and said work is planned to begin this summer in coordination with existing solar arrays.

The measure matters because MSBA reimbursement reduces the local share but requires the city to secure local funding quickly. Joe Traini, the school department supervisor, explained why selected roof sections qualified for MSBA review: “When the initial SOI was submitted to the MSBA, that back section of the roof did not qualify, for two reasons: the age and the condition of the roof.” He said the program’s timetable and reimbursement rules shaped the chosen scope.

Council debate focused on the financial implications. A member of the budget and finance committee described the bond package as a 30‑year financing at about 4.5% that would translate to roughly $253,000 in annual debt service for one of the bond authorizations and a net local cost after estimated MSBA reimbursement of about $4.1 million. Several councilors requested a debt schedule showing multi‑decade impacts and the average-taxpayer effect before final budget adoption.

“Who’s in charge?” one councilor asked, framing the fiscal concern. Another echoed the need for clearer long‑range analysis but said the roof repairs themselves have been a recurring necessity after years of repairs and patchwork.

The council approved both bond orders by roll call. The first bond order (Order 7‑92) passed 11–0; the companion order (Order 7‑93) passed by the same margin. The administration said the city will proceed to secure local funding, complete MSBA steps, go to bid, and aim for substantial completion before the next school year.

Next steps: the administration will manage bidding and contract selection, coordinate solar reinstallation where required, and report financing details to the council as the scope and schedule firm up.