Commissioners waive $1 million cap to speed Burnt Store Road safety improvements
Summary
The board waived the $1 million contract cap for a minor paving/drainage/concrete contract so the county can seek quotes for an estimated sub-$4 million Burnt Store Road safety project, a move staff said will likely shorten procurement by about three months.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
The Lee County Board of County Commissioners voted March 17 to waive the $1 million cap on a standing minor paving, drainage and concrete contract for the Burnt Store Road safety improvement project.
Rob Price of the county DOT told commissioners the estimated cost for paved shoulders and rumble striping is below $4 million; lifting the cap for this project allows the county to solicit quotes from all vendors on the contract and is expected to trim roughly three months from the procurement timeline. Price and DOT staff said they intend to bring a contract back to the board for approval before the summer break.
Commissioners supported the acceleration and noted the qualified contractor pool will have full opportunity to bid. The motion passed with no objection recorded in the transcript.