CTE fieldhouse on track for October completion, district told
Summary
A construction update said the district’s new CTE fieldhouse is on track for substantial completion on Oct. 7 and final completion on Oct. 21, with punch‑list work, final inspections and erosion control measures scheduled in early October.
Get email alerts on the Construction topic
No spam. Unsubscribe anytime.
District staff presented photographic progress and schedule updates for the CTE fieldhouse adjacent to the football field, reporting target dates for final inspections and completion.
The presenter said the project is working toward substantial completion on Oct. 7 and final completion on Oct. 21. Final city inspections were scheduled for Oct. 4 and a punch‑walk for Oct. 7; remaining work listed for the punch list included paint corrections, riprap and erosion control along the new fire lane, handrail installation for new stairs, flooring finishes (rubber flooring, epoxy and carpet), and locker‑room bench installation.
Board members asked practical questions about site finish details, including whether decomposed granite would extend to the edge of the site and whether a continuous concrete pathway would prevent mud tracking into restrooms and the bleachers. The presenter confirmed a continuous walkway connects the new building to the bleacher pathway and said benches are scheduled for installation the following day.
What’s next: The project will proceed through the planned punch list and final inspections in early October; district staff will monitor final items and confirm the project’s substantial and final completion dates.