Corinth council approves $3.3 million impact-fee reimbursement and $400,000 city contribution for wastewater project

Corinth City Council · March 5, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council unanimously approved an agreement with Trioint Homes DFW LLC to reimburse the developer up to $3.3 million in wastewater impact fees for construction of a lift station and force main serving Canyon Lake Ranch/Enclave developments and approved a $400,000 city cash participation for westside lift station improvements.

The Corinth City Council voted unanimously to approve an impact-fee reimbursement agreement with Trioint Homes DFW LLC that authorizes the developer to construct wastewater improvements and receive reimbursements and offsets consistent with the city's adopted impact-fee ordinance.

Public Works Director Glenn Barker presented the project map and cost estimates, telling the council the capital-improvement-plan cost for the wastewater work serving the Canyon Lake Ranch and Enclave areas is "about $6.7 million." Barker said the city previously offset $1.1 million of impact fees and that the proposed agreement would permit reimbursement of about $3.3 million in wastewater impact-fee reimbursements to the Enclave developer (approximately 67% of the CIP share). He also said the city would contribute $400,000 in cash toward needed westside lift station improvements including odor control, pump controls and air conditioning; Barker noted those repairs are already planned in the CIP.

Council members questioned the project's service area and how reimbursements relate to commitments by a neighboring Long Lake development. Staff said the lift station would serve the Canyon Lake Ranch parcels (green, blue and orange areas on the presentation) but would not support other Long Lake parcels. Council members raised that Long Lake had defaulted on prior improvement obligations; one member requested that, if the city proceeds with reimbursement to the Enclave developer, the developer assign any causes of action the developer holds against Long Lake to the city so the city may pursue collection.

A council member moved to approve the agreement, the motion was seconded, and the council voted unanimously. The transcript records the outcome as unanimous but does not list individual vote names or counts.

Why it matters: the agreement lets the developer build necessary wastewater infrastructure (lift station, force main, easement acquisitions) and recover a substantial portion of impact-fee-derived costs through reimbursements. The city's approved $400,000 contribution addresses specific upgrades to the westside lift station that staff said are required irrespective of developer construction.

Next steps: the agreement is authorized; staff and the developer will proceed with construction and coordination on easements and implementation. Council asked staff to return if additional related decisions or assignments of claims are needed.