Summary

Staff presented options to resurface either the high school or middle school tennis courts with high-end estimates near $810,000–$850,000; adding spectator seating or folding the courts into the athletics complex triggers ADA upgrades that significantly increase cost, so district and county are weighing partnership models.

Halifax County Public Schools staff told the joint facilities committee they have evaluated multiple resurfacing options for the district's tennis courts, comparing work at the high school and the middle school.

High-end resurfacing estimates presented to the committee were about $850,000 for the high school and roughly $810,000 for the middle school when pursuing the highest level of renovation. Staff said the cost gap narrows with lower-scope options and that choosing the middle school option tends to reduce infrastructure expenditures because of existing access, grading and electrical differences.

Presenters emphasized that adding spectator seating or formally including the tennis courts within the athletics complex would trigger Americans with Disabilities Act requirements — accessible parking, accessible paths and public toilets — which materially raise total project costs. By contrast, a like-for-like resurfacing with no permanent spectator stands typically does not require those additional ADA upgrades.

To address cost and access, staff described four partnership models for the high school court option: a 50/50 construction split with shared maintenance, a credit structure that offsets school financial obligations, a 70/30 split with the county covering preventive maintenance and electricity, or a school-funded approach that limits public access to avoid ADA-triggering items. The middle-school option was presented as a lower-infrastructure-cost alternative because it likely would not require regrading or additional electrical work to the same extent.

Committee members discussed procurement strategies (change order vs. new RFP) and the use of local contractors for specialized work (tennis-court and track specialists rather than general building contractors). Staff cautioned that final pricing is pending subcontractor returns and that options should be weighed in the context of the overall athletics complex budget and community access goals.

Next steps include refining costs with returned subcontractor pricing and discussing partnership preferences in a joint meeting of the school board and county supervisors.