Summary
During its May 6 meeting the Area Plan Commission forwarded unrepresented show-cause cases to magistrate court and granted multiple 30-day extensions to property owners and representatives working to clean up code violations under the Revitalization Project docket.
Get email alerts on the Code Enforcement topic
No spam. Unsubscribe anytime.
The Decatur County Area Plan Commission used its May 6 meeting to process multiple show-cause matters under the Revitalization Project docket. The panel emphasized that it can grant time-limited extensions or forward unresolved matters to magistrate court; once the office serves papers the court process follows.
The commission voted to forward several cases with no representative present to court, including R2026-9 (James and Bonnie Smith) and R2026-10 (John Hugel). "Having no one, I will need a motion... I make a motion to forward on to the court system, project show cause hearing R2026-9," a member said, and the board voted aye.
When property owners or their representatives appeared, the commission commonly granted 30-day extensions to allow cleanup. In R2026-12 (David and Justin Israel) the board discussed which parcel was under review, recent photos and cleanup plans; the applicants asked for 30 days and the commission granted a 30-day extension. Jeremy Guerrero, representing a land trust for R2026-13 (620 North), said his group had only recently received notice; staff described complaints about trash, vehicles and rodent concerns and the commission granted 30 days for cleanup. Dino Buljubasic, property manager for a White Oak Hill land trust (R2026-14), told the board the structure is uninhabitable, repossessed in 2022 and is being marketed with plans to clear overgrowth and secure windows; a 30-day extension was granted.
Commissioners noted that granting repeated 30-day extensions effectively lengthens the period before court action and that the office retains discretion to move a property to court if progress is insufficient. Several cases (including R2026-8, R2026-11 and R2026-16) were either continued, determined to be under active remediation, or reported closed by staff.
Next steps: Properties with granted extensions must show measurable cleanup within the 30-day period or the office may forward the matter to magistrate court; those already forwarded will proceed through the court docket.