Summary

Council approved using an additional $1,000,000 from 2022 transportation-alternatives SPAT funds for the Stilson Transit Center after staff said $1,000,000 of an earlier federal BUILD grant had been used for professional services.

The Jackson Town Council on May 4 approved a staff recommendation to allocate an additional $1,000,000 of 2022 transportation-alternatives SPAT funding to the Stilson Transit Center project, increasing the town’s total SPAT allocation for the project to $8,388,892.

Public Works Director Johnny Ziem told council staff had originally assumed the project could use the full $7.2 million awarded under a federal BUILD grant for construction when approving a guaranteed maximum price (GMP) contract in December 2024. Ziem said $1,000,000 of that award had been used to pay professional-services costs (Jorgensen Associates), leaving $6.2 million available for construction; to cover the shortfall staff recommended adding $1,000,000 of local SPAT funds.

Councilor Schechter asked whether the county must also approve the change; Ziem said the Board of County Commissioners would take the item up the next morning and both bodies must approve the allocation. Heather Overholser, Teton County public-works director, clarified the SPAT program total and the inclusion of an already-approved $651,000 local match for professional services.