CTE building update: board told the CTE project is on time and under budget at 38.3% complete

Louisa County School Board · April 2, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District staff reported the CTE project has spent $11,018,240.96 (28.05% of budget) and is 38.3% complete; steel work is in place for multiple sections, a bridge structure is being formed, and roof membrane work is slated to begin around April 22.

District staff presented drone footage and progress photos for the new CTE and school building project, describing work by building section and giving a financial and schedule update.

According to the presentation, the project has expended $11,018,240.96 — reported as 28.05% of the total budget — and is approximately 38.3% complete. Staff noted two recorded change orders and listed three payments to the architect/contractor (RRMM) in the current packet.

Construction highlights included completed steel work for sections B and C, a mezzanine area to be poured with concrete in coming weeks, and forms in place for a pedestrian bridge to be erected this summer. Staff said roof sheathing and metal decking work are under way and that membrane installation is expected to begin around April 22, with roughly 1½ to 2 months estimated to make the building weather-tight.

No vote or formal action was required; board members asked scheduling and roof-timing questions and were told the project remains on schedule and under budget as reported.