Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Library Expansion topic
No spam. Unsubscribe anytime.
Wasilla library expansion pushed to spring 2027; estimated construction cost $3.2 million, city share uncertain
Summary
Library Director Zane Tree told the council the expansion’s construction estimate is $3.2 million (furnishings excluded), recommended bidding in 2026 to lock steel prices and targeting spring 2027 groundbreaking and spring 2028 completion. Funding remains uncertain; Tree said the city’s share could range from about $1.3M to $1.7M depending on grant outcomes.
Get email alerts on the Library Expansion topic
No spam. Unsubscribe anytime.
Library Director Zane Tree told the Wasilla City Council the schematic design for the Wasilla Public Library expansion carries a construction estimate of about $3.2 million, not including furniture, and recommended delaying groundbreaking to spring 2027 to improve contractor availability and to run the bidding process later in 2026 to try to lock steel prices.
Tree said the architects estimate roughly a 10-month construction schedule if work begins in spring 2027, putting the likely completion in spring 2028. "We thought we'd be able to start this summer or fall, but the architects recommended going out to bid this calendar year and starting in spring of '27," Tree said.
Tree outlined the funding approach but cautioned many figures remain uncertain. He said earlier planning targeted a mix of about one-third grants (approximately $1.1 million), about $1.3 million from the city and roughly $600,000 from other sources (other governments and fundraising). He later indicated that, "depending on federal and foundation outcomes," the city’s required contribution could be higher — "maybe 1.7 million," he said — and that precise amounts will depend on grant awards and foundation commitments.
On furnishings, Tree estimated an additional $100,000–$200,000 for furniture and fixtures, noting the designers were still preparing multiple options and costings. "They're going to give me options," he said. "My best guess is probably about $100,000 to $200,000."
Tree said staff have submitted a $1 million request for congressional-directed funding and have pursued foundation support. He said the Matsu Health Foundation had indicated interest but would not commit amounts until January 2027; the Rasmuson Foundation’s decision horizon was described as December 2026. Tree described the longer timeline as an opportunity to pursue federal, state and foundation funding and to coordinate with the finance department on how much the city must have ready before going to bid.
Why it matters: the expansion would add capacity and staffing room intended to meet projected community needs for 20 to 30 years. Council members pressed Tree on how much the city would likely need to commit and on alternatives if federal or foundation funds do not materialize. Tree said staff will return with firmer numbers after further conversations with finance and receipt of final cost items from the architect.
Next steps: Tree asked council for questions and said the project timeline will be revisited as final furnishing costs, grant decisions and finance department guidance become available.

