Monona council approves repaint of 400,000-gallon water tower after tests show thinning paint
Summary
Council approved a $288,200 contract (base bid $264,600 plus alternates) to repaint the large elevated tank after thickness testing found thin or exposed areas; staff said the last full paint was in 2006.
Get email alerts on the Infrastructure Maintenance topic
No spam. Unsubscribe anytime.
The Monona council approved a contract to repaint the city’s 400,000-gallon elevated water tank after staff reported areas of thin or failing paint identified in thickness testing.
Staff said the city received 12 bids and that OMT Painting submitted the low base bid of $264,600. Staff recommended two add-ons: spray foam insulation in the tower cone area ($12,000) to reduce condensation and a temperature transmitter with a scale connection ($11,600) to inform operational decisions. The combined recommended contract amount is $288,200; staff noted a contingency of approximately $42,000 and a project budget of $490,000.
Council members asked about the variability of bids and whether the recommended contractors had local experience; staff said they reviewed qualifications and cited examples of L&T’s work in other states and are comfortable with the recommendation. Staff also said the large tower was last fully painted in 2006 and that thickness testing showed thin areas that should be addressed to prevent rust.
A motion to approve the contract was made, seconded and called to a vote; the record shows the motion passed but does not list individual vote counts.