Commissioners approve multiple road, bridge and professional-service contracts; task order added after unpermitted fiber work
Summary
The Boone County Board approved several highway and infrastructure actions March 23: multiple bids were taken under advisement, contracts and quotes for bridge and guardrail work were approved, and a BFNS task order was amended to provide right-of-way oversight after unpermitted AT&T work damaged subsurface drains.
Get email alerts on the Procurement Contracts topic
No spam. Unsubscribe anytime.
Boone County commissioners on March 23 approved a slate of procurement and contract actions covering road preservation, bridge work, guardrail repairs and a professional-services update, and they added a task order to oversee unpermitted fiber work.
Bids were opened for project 2026-11 (liquid road preservation) and for bridge-replacement projects including Bridge 229 and Bridge 285; the board took the bid packages under advisement to allow staff time to review the proposals. The highway department read aloud four bids for the road-preservation project and multiple bids for bridge replacements; staff will return with recommended contract awards after bid review.
The board approved several contract and quote awards at the meeting: execution of a contract for Bridge 70 replacement with Duncan Robertson (contract amount read in the meeting as a not-to-exceed figure), approval of sign-and-barricade rental for the annual road program (low quote read as $54,587), and acceptance of three guard-rail repair quotes for County Road 200 North and two bridges (low-quote amounts read during the meeting). Commissioners also approved the BFNS master services agreement update (an update to a 2017 agreement) and approved an amendment to BFNS Task Order 59 to provide right-of-way oversight for fiber installation in Royal Run subdivision after AT&T began work without approved permits; that oversight amendment increased the task amount to a not-to-exceed $103,400 as read in the meeting and staff said project expenses will be reimbursed by the responsible party.
Terry Larson and other highway staff presented the contracts and explained the need for oversight and repair work. Commissioners moved and voted to approve the listed contracts and amendments. Several dollar figures were read aloud in the meeting and the transcript includes transcription ambiguity on some amounts; the board asked staff to document exact contract totals and post the executed contracts in procurement files.
Next steps: staff will review bids, prepare formal contract awards for the bridge projects, and finalize invoicing/reimbursement for the BFNS oversight amendment.