Bullitt Hill bridge washes out again; county disputes FEMA cost estimate

Henry County Fiscal Court · March 17, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Henry County officials said the Bullitt Hill bridge washed out again and face a funding gap: county estimates place replacement at about $315,000 while FEMA records cited eligibility nearer $90,000. The court discussed temporary access limits and plans to apply for a replacement program in early May.

Henry County Fiscal Court members said the Bullitt Hill bridge washed out again and discussed both short-term access measures and longer-term replacement options.

The court heard that local estimates to replace the bridge are about $315,000 while FEMA has indicated an eligible cost near $90,000, a gap local officials said would not cover removing the existing structure. The court explored temporary fixes — adding concrete fill and imposing a 3-ton load limit — to preserve emergency access while contractors and inspectors assess the site.

“[T]he cost to replace that bridge $315,000, and FEMA seem to think we should be able to get it done for 90,000,” the chair said, noting that most local contractors would not remove the old bridge for $90,000.

County staff said they would await the bridge inspector’s report before deciding whether a short-term concrete fill or a restricted low-load reopening is feasible. Officials also said they plan to apply for a separate bridge-replacement program whose applications open in the second week of May.

Why it matters: the bridge serves local traffic and emergency responders; extended closure affects routes for residents and first responders in parts of the county. The court emphasized limiting heavy trucks on any temporary crossing and prioritizing a permanent replacement through grant programs.

Next steps: inspectors will complete their assessment and the county will submit an application in May for the bridge-replacement program; the court will revisit repair options after the inspection and as grant opportunities develop.