Rolando Vela of Cameron County Drainage District No. 5 told the commission about a $70 million grant portfolio for channel widening and detention ponds, a $2.5M grant to fix a bottleneck under Business 77, and a $13M NRCS award for North Main Drain stabilization.
Get email alerts on the Drainage topic
No spam. Unsubscribe anytime.
Rolando Vela, general manager of Cameron County Drainage District No. 5, gave a detailed presentation to the Harlingen City Commission on flood‑control planning, grant awards, and a proposed parallel channel to increase drainage capacity.
Key points: Vela described the region as an artificial drainage system that needs engineered detention ponds and widened channels to move peak flows. He said the district is pursuing roughly $70 million in grants to widen channels and build detention ponds in the west side of the district; a $2.5 million grant will address a known bottleneck under Business 77 and nearby railroad tracks; and the district secured a $13 million package from the Natural Resources Conservation Service to stabilize and regrade the North Main Drain after recent storm damage.
Work under way and next steps: Vela said project designs are in progress and that some projects will move into construction soon. He described a concept for a parallel channel roughly 4.5 miles long — estimated at $15–20 million — to provide additional relief as development increases impervious surface in the watershed. The district plans coordination with the International Boundary and Water Commission (IBWC) and legislative advocacy to secure direct allocations; Vela said a regional coalition hopes to draft legislation by October and hold a 'day at the capital' on Feb. 10.
Why it matters: Drainage improvements aim to reduce residential flooding that occurred in past storms, protect schools and housing, and improve resilience as Harlingen grows. Vela and city staff emphasized interagency coordination and grant reliance to move the largest projects forward.