Contractor progress reported on Avoyelles Parish school construction; sewer and drainage largely installed
Summary
A district construction update said most sewer and drainage work is complete and crews expect concrete forms for building pads before month'end; rain caused earlier delays, and photos shown during the meeting illustrated manholes and drainage installations.
Get email alerts on the School Construction topic
No spam. Unsubscribe anytime.
Mr. Marcus gave the board a site update on the district building project, reporting that contractors had installed the majority of sewer lines and about 90% of drainage work. He said recent rain caused delays but that the next visible milestone will be concrete forms for building pads, anticipated before the end of the month.
Marcus described the site layout and what the meeting photos showed: catch basins in parking areas, drainage pipe, a sewer manhole where pressure testing occurred, and the relative locations of the arena, career academy and cafeteria. He told the board that much of the current work consists of buried utilities and that visible progress will increase once concrete is poured for pads.
Board members asked about attachments and meeting internet links, and the presenter suggested members could view pictures on their phones or come forward to view them in the room. No formal action was taken; the board thanked the presenter and moved on to financial reports.