Council approves purchase of screw press to improve wastewater dewatering, cut hauling costs

Sedro-Woolley City Council · March 25, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council authorized buying a custom screw press (equipment cost ~ $413,000) to replace an underperforming belt press at the city's wastewater plant; staff said the equipment should improve solids dryness, cut hauling costs by an estimated 70% and reduce regulatory risk.

Public Works told council the plant's current belt press delivers marginal dewatering (7–11% solids) and that a demonstrated screw press produced >20% solids during a weeklong trial. Staff recommended ordering a custom screw press sized for up to 4 million gallons per day to accommodate current and future plant loads. The council approved the equipment purchase to begin manufacturing; separate contractor work to modify and install the unit will follow and is expected to be funded from sewer reserves.

Staff estimated equipment cost around $413,000; installation and building modifications are additional and the overall project is expected to reduce hauling costs by roughly 70% and lower operational risk during high flow seasons. The screw press manufacturer will provide installation support; full contractor procurement and installation will be pursued after manufacturing lead time (five to six months).