County outlines timeline and cost limits for new Courthouse Annex; GMP amendment on today's agenda

Commissioners Court of Brazos County · March 24, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Project management presented finalized design, a fourth floor carried as shell space, a completed MOU with TxDOT for a secure bridge over Texas Avenue, and a planned notice to proceed in April; a guaranteed maximum price amendment is on the court's agenda.

Trevor Landsdown, director of project management, gave the Commissioners Court a detailed progress report on the Courthouse Annex project at 101 North on March 24.

Landsdown summarized the project's evolution: the county acquired the Bryan ISD administration property in 2021, demolished the existing structure in 2023 and engaged Plan North and construction manager SpawGlass to develop a four‑story annex with an attached parking garage and a secure bridge connecting to the courthouse. The court previously approved a $59 million construction cost limitation tied to adding a fourth floor as shell space.

He said the project team carried core infrastructure (elevators, restrooms, sprinklers) for a fourth floor but left fit‑out to be scheduled when specific tenant departments move in; Landsdown described the fourth floor as available shell space and said the $10 million figure referenced that shell work, not a finished build‑out. He reviewed department placement: transactional services and Justice of the Peace functions on the first floor, Adult Probation occupying the second floor, and the Public Defender planned for upper floors.

On schedule and approvals: Landsdown said a memorandum of understanding with TxDOT to allow the secure bridge over Texas Avenue is executed, the city approved a special use permit this morning, and 100% construction documents were expected the same week. SpawGlass’ notice to proceed was scheduled for April 6 with a tentative groundbreaking planned for April 21; substantial completion is projected at roughly two years.

Why it matters: The project consolidates several county functions, expands space for growing offices (probation, public defender) and requires traffic mitigation downtown during bridge erection. Landsdown said the team is preparing a traffic control/media campaign to notify downtown users.

Next steps: The court was asked to consider a guaranteed maximum price amendment from SpawGlass on the same agenda; staff said material testing, permitting and final documents were in motion before a notice to proceed.