Advisory committee urges rate study to consider redistributing $12.2M Substation 4 cost

Utilities Advisory Committee · October 1, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Boulder City's utilities advisory committee recommended that the rate study evaluate spreading the estimated $12.2 million Substation 4 rebuild over 2028'031 and examine partial design funding in 2027 to avoid steep rate spikes; the motion passed unanimously.

Carol Lelis, the city's CIP coordinator, reviewed the utilities five-year capital improvement plan for fiscal years 2027'031, saying the plan "includes 20 projects for a combined cost of 50.7 million," with seven projects totaling $6.8 million in fiscal 2027. The plan lists electric, water and wastewater projects and is intended as a living document that staff revisit annually.

Committee discussion focused on timing for a multi-year Substation 4 rebuild that staff estimated at roughly $12.2 million for 2029'031. Members said accelerating or redistributing the work would smooth the conversion from 4 kV to 12 kV and reduce the risk of a large rate increase in outer years. Committee members noted procurement lead times for transformers and breakers and that cash-flow limits might constrain moving work earlier.

After discussion, a member moved that the committee advise council and staff to "distribute the total cost for Substation 4 rebuild over a four-year period of 2028 through 2031 and also consider a funding partial design during 2027." Another member seconded; the motion passed unanimously.

Staff said the rate study now under procurement will evaluate revenue requirements and cash-flow implications that would be needed to implement any schedule adjustments. Members asked that the rate-study scope explicitly consider spreading Substation 4 costs across additional years where feasible so rates can be levelized and large year-over-year jumps avoided.

The committee did not bind council or staff to a construction schedule; instead the motion advises that the rate study model scenarios that include redistributed cash flow and, where feasible, partial design work in 2027. The committee will monitor the rate-study scoping and results through its liaison and via future agenda updates.