Grant-funded signal at Bailey Boswell and Jarvis could reach construction in 2028, staff says

Traffic Safety Advisory Board · May 8, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff reported the Bailey Boswell and Jarvis signal is grant funded and that 60–90% plans have been submitted to TxDOT; the earliest construction date provided was October 2028, though staff said they are requesting that date be moved up.

The board received an update on a grant-funded traffic-signal project at Bailey Boswell and Jarvis.

Staff said the project has progressed through design (60–90% plans submitted to TxDOT) with minimal comments from TxDOT so far. Construction was estimated as early as October 2028 under the current schedule; staff said they have requested TxDOT allow the design to be moved up to October 2027 if possible, but outstanding franchise-utility clearance letters are delaying any schedule acceleration. Staff noted the project is grant funded and that the city is not the primary designer on the effort.

No formal action was taken on this agenda item; staff will continue coordination with TxDOT and franchise utilities and update the board when more information is available.