Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Infrastructure Projects topic

No spam. Unsubscribe anytime.

DeSoto County accepts Agri‑Education Center waterline closeout, extends Feathers contract

DeSoto County Board of Supervisors · February 2, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Board accepted closeout documents for the Agri‑Education Center waterline project, setting the one‑year warranty from Jan. 9, 2026, and authorized an extension of Ralph Feathers' contract for the Agri‑Education Center; the Board instructed the Board Attorney to revise the contract.

DeSoto County accepted final closeout documents for the Agri‑Education Center waterline project and extended a related contractor agreement at its Feb. 2 meeting.

Will Bush of Waggoner Engineering reported that all work on the Agri‑Education Center waterline was completed and inspected as of Jan. 9, 2026, and asked the Board to approve the final acceptance letter and the final construction change request that sets the one‑year warranty start date of Jan. 9, 2026. The Board approved the closeout documents and authorized Board President Jessie Medlin to sign.

Separately, County Administrator Andrea Pettigrew told the Board that Ralph Feathers' contract for the Agri‑Education Center expired Dec. 31, 2025. The Board voted to extend Mr. Feathers' contract and authorized the Board Attorney to revise the contract terms as needed.

Board documents and the final change request will be included in the official minutes and the warranty period will begin Jan. 9, 2026.