Ann Arbor staff outline summer construction on Kingsley, Catherine and Ingalls streets
Summary
City presenters described three overlapping summer projects that will add a two-way cycle track on Catherine Street, replace a Kingsley/Ingalls water main and rebuild a roundabout; work begins in May and will stretch into October, with traffic and transit impacts.
Get email alerts on the Summer Construction topic
No spam. Unsubscribe anytime.
City staff outlined three overlapping construction projects this summer that will affect Kingsley, Ingalls, Catherine, Zena Pitcher and Ann streets and said the work will include a two-way cycle track, water-main replacement and a rebuilt roundabout.
Presenter Cynthia said the presentation covered three distinct projects managed by separate project leads and shown on a shared map. “This summer, we have 3 projects in this area that are being managed by 3 different project managers,” Cynthia said. She identified project leads for the different sections and noted some names were recorded inconsistently in the transcript.
Why it matters: the projects combine utility work, street resurfacing and bicycle- and pedestrian-safety upgrades in a compact neighborhood, which staff said will require phased closures and signal changes that affect motorists, transit riders and people biking or walking in the area.
Project scope and traffic controls: Cynthia described the Catherine Street project as installing a two-way cycle track with bump-outs, pavement markings and city posts. She said signal phasing at Division and Catherine will be adjusted to include a dedicated pedestrian and bicycle phase to improve crossings. On Kingsley and Ingalls, staff described a water-main replacement and storm repairs alongside street resurfacing; the work will incorporate a designated local cycling corridor and crosswalk and speed-management measures where appropriate. For the Zena Pitcher, Catherine and East Ann Street project, Cynthia said crews will do resurfacing, pedestrian and bicycle safety enhancements, signal upgrades at Ann Street and Zena Pitcher Place, underground stormwater improvements and rebuild the Observatory Street roundabout.
Timing: staff said work will begin in May on the Kingsley segment between Detroit Street and North State Street and that crews plan to finish initial work before the city’s art fair. In June, they will move to Kingsley between North State and Angle Street and begin work on Angle Street while continuing Catherine work. Staff said July and August will see ongoing Kingsley and Ingalls work, with the west section of Catherine (west of Glen Avenue) expected to be finished in July and Catherine east of Glen and Zena Pitcher wrapping in August; Anne/Ann Street and roundabout work will begin in August. Cynthia said remaining work will continue into September and that Anne/Ann Street work should be completed by October while Kingsley and Ingalls may extend into October.
Project managers: the presentation named project leads for the different sections. Two project managers were named consistently in the transcript (Cyrus Nahidi and Mark McCullough). The presenter also named an Igor as a project manager for parts of the work, but the transcript records that last name inconsistently; the transcript variants are noted in the provenance and clarifying details.
What the presentation did not include: the presenter described scope and schedule but did not specify project budgets, funding sources or exact lane-closure schedules; staff referred listeners to the city’s road-and-lane-closures page and the three project pages on Engage Ann Arbor for detailed timelines and maps.
Next steps: staff said timely updates and maps will be posted online and that residents with questions can reach out through the Engage Ann Arbor project pages.