Belmont County advances water and sewer work: Pennwood bids advertised, engineering contracts and change order approved
Summary
The commissioners authorized bid advertising for the Pennwood Lift Station and Force Main, approved engineering agreements for multiple water‑system projects and approved a $99,539 change order for the Eastside Lift Stations project; the board recorded engineering estimates and noted funding sources including ARPA and capital improvement funds.
Belmont County Commissioners on Feb. 25 authorized several actions to advance water and sewer infrastructure projects: formally advertising bids for the Pennwood Lift Station and Force Main project, approving engineering agreements for multiple water main upgrades, and approving a change order that increases an Eastside Lift Stations contract by $99,539.
The board authorized advertisement for bids for the Pennwood project, describing the scope as about 3,340 linear feet of 6‑inch HDPE force main to be installed by open trench, a submersible duplex pump lift station, valve vault and related…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat