Dunn County approves multiple road payments and awards two construction bids to Trotter Construction
Summary
The Dunn County Commission approved pay requests for several road projects (including $821,478.79 to CSI for 119th Avenue SW and $156,520.88 to Martin Construction for 99th Avenue SW) and awarded the Spring Creek and 11th Street bids to Trotter Construction after bid verification.
Get email alerts on the Infrastructure Projects topic
No spam. Unsubscribe anytime.
The Dunn County Commission approved several construction payments and awarded two project contracts during its regular meeting.
Darren, the county’s project lead, recommended Pay Request No. 1 for the 119th Avenue Southwest project for $821,478.79 to CSI, noting the amount included liquidated damages; the commission approved the payment by roll-call vote. Commissioners also approved Pay Request No. 3 for Martin Construction on the 99th Avenue Southwest project for $156,520.88 after staff confirmed outstanding site items would be addressed and that retainage remained.
The commission opened multiple bids for Spring Creek and the 11th Street project. Staff verified low bids and recommended awarding the Spring Creek box culvert contract (CP132607) to Trotter Construction for $593,635.80 and the 11th Street project (CP132203.1) to Trotter Construction for $912,897.96. The board voted to award both bids following staff verification and the usual roll-call procedure.
Chair noted staff will review bids and project quantities as projects progress, and retainage will be held until final quantities are agreed. Jeremy, the engineer verifying bids, said Trotter has established local experience and was qualified to perform the work.
Next steps: staff will finalize contract documents and begin preconstruction coordination with the awarded contractors.