Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
Commissioners hear $40 million estimate for 42-inch water main rehab and plan to hire owner's advisor
Summary
Staff outlined a proposed rehabilitation of a nearly 80–90-year-old, roughly 7-mile, 42-inch reinforced concrete water main serving about 50,000 customers and requested hiring Arcadis as owner's advisor to manage design procurement and project oversight; commissioners raised concerns about proceeding under an interim director and asked for more design work before committing.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
County staff told commissioners of a proposed rehabilitation of a 42-inch reinforced concrete water main — roughly 7 miles in length and described as nearly 80–90 years old — that serves the county’s system and about 50,000 customers. Staff said initial, non-final estimates for rehabilitation were on the order of $40,000,000 and emphasized that design and engineering were not yet complete.
To manage the project, staff recommended hiring Arcadis Incorporated as the owner’s advisor to provide project management, hydraulic modeling, and procurement assistance. Staff clarified Arcadis would serve as an advisor and would not perform the final design or construction; final design, engineering and construction would be procured separately.
Commissioners asked whether the project should be paused until a permanent Water & Sewer director is hired and sought clarity on how the $40 million estimate was derived. Staff said the project has been studied for about three years, initial inspections have been taken, and final construction drawings and cost estimates would follow; they also said the Board could pause the effort if it wished. One commissioner noted the complexity of the lining approach and that comparable installations might require overseas travel for observation of techniques.
No contract with Arcadis was executed at this meeting; staff said a resolution to hire the consultant would be placed on a future agenda for formal consideration and that subsequent design and cost updates would be provided at each step.
