Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Infrastructure Funding topic
No spam. Unsubscribe anytime.
Brookfield trustees weigh tax‑rate referendum to fund 20–25‑year road program and $25M community center
Summary
Trustees reviewed a staff plan to use a limiting‑rate referendum to permanently fund a 20–25‑year street program (aiming to preserve current street‑portion tax levels) and discussed a separate bond referendum to finance a community center (estimated $25M–$27M), with staff recommending sequencing, consultant outreach and outreach to residents.
Get email alerts on the Infrastructure Funding topic
No spam. Unsubscribe anytime.
Village of Brookfield trustees spent the bulk of the Committee of the Whole meeting on Oct. 13 evaluating how to pay for two large capital priorities: a multi‑decade road program and a proposed community center.
Doug, the village finance lead, told trustees the preferred path for the roads is a limiting‑rate (PTEL) referendum that would increase the village’s capped property‑tax rate so that funds currently used to pay maturing bonds would instead be dedicated to ongoing street maintenance. “The reason we would look at a referendum…was we do not have the available funds, of course, to finance either or one of these projects,” Doug said, adding the village model envisions a 20‑year program that would require roughly $4.0 million annually or a 25‑year model that would cut roughly $500,000 per year.
Derek, the village’s engineering advisor, said industry practice targets a 20–25‑year useful life for asphalt streets and that Brookfield’s prior bond program (about $22 million in 2016–2020) temporarily raised the pace of repairs; current funding would leave the village on roughly a 50‑year cycle without change. “If we’re going to do a 20‑year street program, the target would be about two miles a year,” Derek said.
Financial adviser Andrew Kim told the board how the referendum could be structured to avoid a one‑time punitive spike in tax bills when the new rate is imposed: if the referendum passes when some bond levies still appear on the tax rolls, the village can use new PTEL capacity to abate bond levies so the portion residents pay for streets remains roughly the same. “You would have an additional $2.7 million of PTEL dollars plus the $1.6 million that you’re still paying on the bonds,” Andrew said, describing mechanics trustees could use to avoid a short‑term tax‑bill jump.
On the community‑center question, staff presented the feasibility study result and a financing scenario to bond for a new facility. The packet used a $25 million baseline but noted construction escalation could push a 2027 project closer to $27 million; staff estimated an example homeowner impact in the scenarios shown (roughly $350/year for a $300,000 home in one modeled case). Staff recommended addressing the road referendum first (Nov. 2026 was discussed as a timing target) and then pursuing a separate community‑center referendum in 2027 after further public education and consultant advice.
Trustees discussed an alternative route — creation of an independent park district that could levy and bond separately for a center — but staff warned that route could introduce delay, require citizen petitioning to put a district question on the ballot, and risk a newly elected park board adopting a substantially different plan. Trustees asked staff to gather more information, including: updated cost escalation assumptions (staff flagged a $27M estimate for 2027), further modeling of the tax‑rate mechanics, and the feasibility and timing tradeoffs of a park‑district route versus bonding under the village.
Staff also recommended engaging referendum consultants to test messaging, sequencing and election timing. Trustees did not vote on a referendum tonight; they directed staff to continue refining numbers, consider consultant input, and bring more detailed public‑engagement and timing recommendations back to the board.

