Planning commission approves two‑year extension for Carrier Group and allows up to three model homes
Summary
The Town of Farmington Planning & Zoning Commission granted Carrier Group a two‑year extension of conditional subdivision approval for Winter Creek Place and approved construction of up to three model homes during the conditional period, after discussion of construction delays, DEEP inspections and possible conditions tied to infrastructure.
Get email alerts on the Subdivision Model Homes topic
No spam. Unsubscribe anytime.
The Town of Farmington Planning & Zoning Commission voted to grant Carrier Group a two‑year extension of conditional subdivision approval for the Winter Creek Place development and approved the company’s request to construct up to three model homes while the subdivision remains conditionally approved.
Developer Johnny Carrier told commissioners that progress on the 25‑lot Winter Creek Place section has been slowed by unanticipated ledge during sewer work and early winter weather, and that the project’s conditional approval expires in May. “We’re requesting a two‑year extension on a conditional approval … and … for up to three model homes to be constructed during the conditional approval process,” Carrier said during the presentation.
Carrier described work completed on the first phase: sewer installation for Winter Creek Place, most of the storm drainage and construction of the detention basin. He said off‑site work and the Cold Spring Lane portion remain, and that finishing the first phase would reduce the town’s bonding requirement. He said that, if he sought final approval now, he would need to post a large financial guarantee: staff and the developer discussed that final approval requires bonding for remaining infrastructure and Carrier said he would otherwise have to post roughly $1.5 million in cash, a surety bond or a letter of credit to secure final approval on all infrastructure.
Commissioners pressed Carrier on safeguards if model homes are built before all shared infrastructure is complete. Several asked for a condition ensuring model homes be limited to lots where sufficient infrastructure and protections (conservation markers, silt fence, stabilized roadway surface) are in place. Carrier said he generally plans to build one model on a corner lot but preferred flexibility to add a second or third in the first development if needed.
The commission debated limiting the number of model homes or tying model‑home permits to a defined level of completion on the rest of the subdivision. After discussion the commission moved and seconded a motion to approve Carrier’s request for a two‑year extension and to authorize up to three model homes on the parcels that are part of the Winter Creek Place/Cold Spring Lane subdivision. The motion carried; the transcript records one commissioner opposing and several abstentions, and commissioners announced that the motion passed.
Why it matters: granting model‑home permissions while an approval remains conditional allows a developer to show prospective buyers physical product before final subdivision bonding is posted. Staff emphasized that a model home still requires a building permit and that state and town rules, as well as any specific conditions the commission imposes, govern when lots and homes may be marketed or sold.
What’s next: Carrier said he expects to return for final approval of the first phase within a few months; any work not completed at the time of final approval must be bonded to protect the town and future homeowners.