Committee backs $49,656.79 change order to add 8‑inch waterline and hydrant at South Terrebonne Middle
Summary
The committee recommended approval of a $49,656.79 change order to add an 8‑inch waterline and a fire hydrant at South Terrebonne Middle School per the local fire marshal; funding sources cited were FEMA reimbursement and disaster recovery funds and staff explained hydrant location and engineering reasoning for an 8‑inch connection.
Get email alerts on the Fire Safety Infrastructure topic
No spam. Unsubscribe anytime.
The committee recommended the board approve Change Order #1 for South Terrebonne Middle School in the amount of $49,656.79 to install an 8‑inch waterline and add a fire hydrant at the middle school bus entry per the local fire department’s request.
Staff said the scope includes approximately 575 feet of 8‑inch PVC main, two new hydrants, valves, valve boxes, precast valve pads and associated work. The local fire department had requested an additional hydrant to improve fire protection for the new middle school and the existing high school. Staff explained that calculations showed an 8‑inch connection was required to maintain adequate pressure and flow to both hydrants and that one existing hydrant needed replacement due to corrosion.
Funding for the change order was described as FEMA reimbursement ($44,691.11) and district disaster recovery funds ($4,965.68). Board members asked who is responsible for ongoing hydrant maintenance; staff said local fire departments typically maintain hydrants and the water line is owned by Consolidated Waterworks, requiring a servitude around the line.
The motion (mover Mr. Dehart; second Mr. Harding) was made and no objections were recorded at the committee level.