Officials propose state construction management pilot to improve delivery on large public projects
Summary
DAGS and other witnesses told the committee SB 2543 would create a pilot office to provide independent design review and on-site oversight of large state construction projects. Proponents said additional technical review could reduce delays and cost overruns; critics urged training and a task force as alternatives.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The House Finance Committee heard SB 2543, which would create a pilot Office of State Construction Manager to provide independent design review and inspection services for large Department of Accounting and General Services (DAGS) and Department of Education projects.
Supporters, including DAGS officials, testified that large state projects — particularly those in the $20 million-plus range — would benefit from additional licensed engineering and inspection capacity. The DAGS controller said the pilot could relieve overworked inspection staff and provide a second set of eyes on design and construction issues.
Opponents and cautioning witnesses, including a retired construction engineer, argued for alternatives such as a non-legislative task force on construction efficiency and investment in training existing DAGS personnel. Contractors and union representatives testified in favor of centralized oversight that includes licensed civil, mechanical and electrical engineers, strong inspection protocols and a clear delineation of decision authority between design-build and design-bid-build procurement paths.
Committee members pressed on how the pilot would work with existing DAGS and DOE functions, how to staff the office with the required disciplines, and whether it would reduce or add to project timelines and costs. DAGS officials said the pilot targets projects above a threshold intended to capture the most value from added oversight and that the office would be evaluated as a limited pilot.