ODOT seeks multi‑year time extension for Abernathy Bridge work; Oregon City wins commitment to negotiate business‑focused IGA
Summary
ODOT told the Oregon City Commission that completing the Abernathy Bridge seismic retrofit will extend into 2027–28 and asked to keep temporary work areas in place; the commission unanimously directed staff to negotiate an intergovernmental agreement setting signage, business‑access and other deliverables before any further extension is approved.
The Oregon City Commission on April 1 heard a detailed presentation from the Oregon Department of Transportation on delays and remaining work for the Abernathy Bridge widening and seismic retrofit, and unanimously directed staff to negotiate an intergovernmental agreement (IGA) that would set local deliverables for signage, business access and other mitigations.
ODOT Region 1 manager Ryan Winshimer told the commission the bridge contractor is ‘‘making progress’’ but that schedule changes and unexpected structural work extended the project. ODOT project managers said major bridge work and large equipment are expected through spring–fall 2027, the agency anticipates barges and cranes removed by the end of 2026, soil‑stabilization work will occur in 2027–28 and final landscaping and a plant‑establishment period would follow in 2028.
Why it matters: businesses along the river told the commission the staging and appearance of the work have driven customers away and caused steep revenue declines. Several business owners urged stronger, enforceable commitments from ODOT — particularly signage that…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat