The commission closed the hearing and issued an Order of Conditions for 665 Central Avenue (DP file 234-963), approving limited work in the 50-foot buffer for invasive removal and plantings, requiring an infiltration O&M plan and two-year monitoring with a 75% survival standard.
Get email alerts on the Land Use topic
No spam. Unsubscribe anytime.
The Needham Conservation Commission voted March 26 to issue an Order of Conditions for work at 665 Central Avenue (DP file 234-963), including a limited waiver to permit invasive-species control and revegetation inside the 50-foot buffer where necessary.
Diane (Field Resources), the applicant’s consultant, told the commission the revised plan adds an invasive-species control area outside erosion controls (mechanical removal only, no pesticides), expanded planting (10 trees and 30 shrubs) and an O&M plan the homeowner signed for infiltration units. She said pre-installation test pits will be completed prior to installing recharge units and that plantings are intended to improve resource-area habitat.
Commission staff asked for confirmation about retaining-wall extent, whether any work would affect a potential vernal pool, and debris removal protocols; Diane said debris would be removed and the homeowner understands the O&M obligations. Commissioners also required a signed infiltration operations-and-maintenance plan and two-year monitoring of mitigation plantings with a 75% survival threshold.
A motion to waive the 50-foot no-disturb restriction for the limited invasive-removal and planting work and to waive the local fee passed by roll call. The commission then issued the Order of Conditions with conditions including: submittal of soil test-pit data for the infiltration system prior to breaking ground, invasive-species management by hand or mechanical means only, planting of 10 native trees and ~30 native shrubs, and a two-year monitoring report documenting 75% survival or corrective actions.
The hearing had been closed earlier in the meeting; the OOC was approved following a staff presentation of special conditions.