Hutchinson approves two street‑improvement contracts and assessment plans after public hearings
Summary
After public hearings, the Hutchinson City Council approved contract awards and assessment resolutions for two 2026 street-improvement lettings covering Edmonton Avenue and a multi‑neighborhood package; council also confirmed assessment payment options and construction timelines.
Get email alerts on the Streets topic
No spam. Unsubscribe anytime.
The Hutchinson City Council on March 24 approved contract awards and adopted assessment plans for two 2026 street‑improvement lettings, following public hearings and a question‑and‑answer period with city engineering staff.
City Engineer Brandon Braithwaite summarized Letting No. 1 (project 26‑01), a full‑depth reclamation along Edmonton Avenue from just east of Culver’s to Jefferson Street that includes sidewalk repairs, repaving the north‑side trail and a pilot for brighter pavement markings. He told the council the low bid from W.M. Mueller & Sons came in about 15% under the engineer’s estimate and that assessments will make up roughly 1% of the project’s funding; the remainder is primarily municipal state aid.
The nut graf: after hearing residents’ questions about irrigation markers, utility locates and access, the council closed the public hearing and approved the resolutions to adopt assessments and accept the low bid.
During a second hearing on Letting No. 2 (projects 26‑02), staff described three project areas — Boulder Street and Boulder Court, Larson Street, and a cluster of neighborhood streets including Bradford, Randall, Sherwood, Elks and Orchard — using full‑depth reclamation with limited curb and sidewalk repair. Brandon said this package includes more water impacts (valve and hydrant replacements), installation of perimeter edge drains to improve base conditions, and an engineer’s estimate near $2.4 million; the low bidder, W.M. Miller & Sons, submitted a bid roughly 11% below estimate. Funding sources cited were stormwater, water and wastewater funds plus about 25% in special assessments for benefiting properties.
Residents used the public‑comment period to press for details on schedule, driveway access during deeper subgrade work, mailbox and garbage handling, tree removal for emerald ash borer, and how assessments are billed. A recurring clarification from staff: assessment rates were calculated before bidding and are based on parcel frontage; because bids came in lower than expected, the assessment calculation does not automatically change. Staff outlined payment choices: a lump‑sum payoff (no interest if paid by the stated date) or placement on the property tax roll spread over up to 10 years with interest, typically prime plus 1% according to the city’s explanation.
Council votes were taken by voice; hearings were closed and the council approved the resolutions that adopt assessments and award contracts for both lettings. Staff said construction is expected to begin in late May with most projects aimed to finish by early–mid August, and that inspectors and the contractor will coordinate staging, temporary mailboxes and notices for planned water shutoffs.
What happens next: staff will finalize schedules with the contractor, notify affected property owners about locating utilities and assessment payment deadlines, and implement periodic resident communications during construction.