Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Board Votes Contracts topic

No spam. Unsubscribe anytime.

Hinsdale board approves Robins Park playground contract and ratifies $38,310 in emergency water‑main repairs

Village Board of Trustees of the Village of Hinsdale · March 16, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Trustees approved a $312,653.70 contract for a new Robins Park playground and ratified emergency water-main repairs totaling $38,310; the board also approved accounts payable for March 4–16, 2026.

At its March 16 meeting the Hinsdale Village Board approved a second‑read contract with D&J Landscaping, Inc. (Shorewood, Ill.) for installation of a new Robins Park playground in an amount not to exceed $312,653.70, including alternates. Trustees discussed the project’s timeline, landscaping and accessible features; staff said construction is expected to begin in April 2026 and end in June 2026.

The board also ratified emergency water‑main break repairs performed by a contracted plumbing company in the amount of $38,310. Public‑works staff explained there were multiple concurrent leaks (including several on Sixth Street) attributable largely to freeze‑thaw ground shifting and pipe failures in older infrastructure; the board voted to expense the repairs from the water‑system maintenance account and keep an existing purchase order open for future urgent repairs.

On the consent agenda trustees approved accounts payable for March 4–16, 2026 totaling $1,245,053.15. All three items were approved by roll call.