San Antonio corridor project to require Caltrans, FHWA approvals; staff estimates documentation by March
Summary
City staff told the Complete Streets Commission the San Antonio road improvement will rely on a master agreement with Caltrans and a supplemental FHWA agreement; staff expects exchange and review with those agencies to take several months and projected full documentation around March, followed by extended design and public engagement.
Get email alerts on the San Antonio Project topic
No spam. Unsubscribe anytime.
City staff said the San Antonio corridor project will move through a multi-step federal and state approval process before major design work and outreach can begin.
Stephen briefed the commission that staff will seek council authority to execute a Caltrans master agreement and then sign a supplemental agreement with Caltrans and the Federal Highway Administration. He estimated each step — Caltrans review and FHWA review — could take about a month to a month-and-a-half, and that the city is realistically looking at completing the necessary documentation around March before issuing a request for statements of qualifications or hiring consultants.
Stephen said the San Antonio work is federally funded for the bulk of construction with a city match (he described it as separate from the annual CIP overlay budget) and that, because the corridor crosses jurisdictions and may affect future downtown growth, the design scope must incorporate traffic-impact studies, school impacts and extensive public information. "Once that master agreement is executed then I need to execute a supplemental agreement with Cal Trans or Federal Highway Administration," he said, and added the full design/outreach process could last a year to a year-and-a-half.
Why it matters: Commissioners were warned the San Antonio corridor is high-profile and visible; staff emphasized careful public engagement and interagency coordination, noting nearby jurisdictions (including Mountain View) have already expressed interest in the corridor’s design because it crosses boundaries.
Next steps: Staff will pursue council authorization for the master agreement and return with timing and staffing plans. The commission discussed the possibility of a dedicated San Antonio project team and staff plans to supplement existing staffing with consultants for public engagement and design.